2009
Master plan approved by the local authorities
2009
Acquisition of the land and appointment of a project manager and an infrastructure designer
2010
Title deed issued to Tunis Bay Project Company
2014
Approval by the local authorities of subdivisions for phase 1 and 2
2015
Groundbreaking infrastructure of phase 1
2016
Groundbreaking of construction work of the golf course and construction work of the first 127 villas of the Golf Residence
2018
Presentation and showcasing of the mockup village of phase 1 of the Golf Residence